Which of the following is not part of the Start Up documents?

Prepare for the Mississippi NASCLA and Residential Exam. Test yourself with multiple choice questions, each with detailed explanations. Ace your exam!

The list of supplies is not typically considered a part of the startup documents in a construction project. Startup documents generally include essential planning and management tools that help organize and set expectations for a project.

The project manual includes crucial information such as the project specifications, contracts, and the rights and responsibilities of all parties involved; it is a necessary component for guiding the execution of a project. The construction schedule outlines the timeline for project phases and critical deadlines, providing a framework for how the work will progress. Meeting minutes are important for documenting discussions, decisions, and actions taken during project meetings, ensuring all stakeholders are aligned and informed.

In contrast, while a list of supplies is helpful for procurement and managing materials, it does not typically fall under the formal initial documents that set up the project. Therefore, its exclusion from the startup documents makes sense in the context of project management and construction practices.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy