Which is NOT a method for delivering options on a construction project?

Prepare for the Mississippi NASCLA and Residential Exam. Test yourself with multiple choice questions, each with detailed explanations. Ace your exam!

The method identified as not being a conventional delivery option for construction projects is Integrated Planning. In the context of construction project delivery, the main recognized methods are Design Build, Traditional System, and Construction Management.

Design Build is a streamlined approach where both design and construction services are contracted by a single entity, fostering better communication and collaboration. The Traditional System, often referred to as Design-Bid-Build, separates the design and construction phases, requiring multiple contracts and often leading to a longer project timeline. Construction Management involves a professional construction manager hired by the owner to oversee the project, ensuring that the design is executed effectively and within budget.

Integrated Planning, while it might involve collaboration and coordination efforts similar to other methods, is not formally recognized as a standard delivery method in the construction industry. It does not encompass the contractual frameworks that define the other methods listed. As such, Integrated Planning does not fit within the established categories of project delivery options used in the construction sector.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy