A Construction Change Directive allows the owner to initiate work prior to full negotiation with whom?

Prepare for the Mississippi NASCLA and Residential Exam. Test yourself with multiple choice questions, each with detailed explanations. Ace your exam!

A Construction Change Directive (CCD) serves as a tool for project owners, allowing them to modify the project scope without the need for complete agreement on all terms with contractors or subcontractors before work begins. The CCD is particularly useful when immediate changes are necessary to advance the project or to address unforeseen circumstances. By using a CCD, the owner can direct the contractor to proceed with specified changes while the exact terms of the additional compensation and associated contract modifications are still under negotiation.

The choice that states "No one" aligns with this concept, as it indicates that the owner can issue a directive to the contractor without needing consensus from any other parties, including subcontractors or suppliers, before initiating the required work. This flexibility is important in maintaining project momentum and ensuring timely responses to changes, even before negotiations are finalized.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy